Police emergency: 911115 W. Main Street · (513) 732-5350

Roads & Transportation

Keeping Owensville moving

Find road improvements, bridge projects and closure information for Owensville and nearby travel routes, with links to the agencies responsible for the work.

Information reviewed October 30, 2026. Project schedules can change. Check official closure notices before traveling.

Know the status before you go. A planning entry does not mean construction has begun. Some official project pages retain older schedules; those projects are marked below. A project listing is not confirmation of an active closure.

Planned work in and near Owensville

Select a project to see its location, schedule, official links and available pictures.

Main Street / U.S. 50 sidewalks and crossingsPlanned • FY 2026 environmental phase • Construction date not confirmed

Project: PID 124681 / CLE US 50 11.47
Location: Just east of Johnnytown Road to the Clermont County Public Library.
Sponsor: Village of Owensville.

The regional transportation program describes new sidewalks and pedestrian crossings on the north and south sides of Main Street. Its listed phase is environmental work in fiscal year 2026, with $116,419 shown for that phase. This is not a verified construction budget or a construction start date.

Official OKI project listing — search for PID 124681 · Regional project map

S.R. 132 bridge over Stonelick CreekPublished spring–fall 2026 schedule • Current status needs confirmation

ODOT PID 102771: The bridge is immediately south of Quitter Way Road, north of U.S. 50. Work includes a deck overlay, edge repairs, painting and guardrail improvements.

The published schedule calls for spring–fall 2026 construction and a 30-day S.R. 132 closure during the work. The reviewed listing still described pre-construction, and the project page could not be retrieved during final checking. No active closure dates were confirmed.

Official ODOT project page (availability may vary) · Check current restrictions on OHGO

Confirm with ODOT District 8: 513-933-6517 · D08.PIO@dot.ohio.gov

Belfast-Owensville Road bridgePublished summer–winter 2025 schedule is older • Completion status unconfirmed

Structure: C10-2.69. CCTID describes replacement of a deficient bridge, with an estimated construction cost of $767,550.

The detailed page retains summer 2025 construction and winter 2025 completion dates, while the overview still includes the project in its construction list. These listings do not establish its present closure or completion status.

CCTID location map for the Belfast-Owensville Road bridge project
Official project location map. Source: Clermont County Transportation Improvement District. Select the map to enlarge it.

Official bridge project page · Contact CCTID for an updated schedule

Jackson Pike bridge replacementFuture county project • Dates not published

Structure: CC62-22. Listed among the County Engineer’s future projects. The detail page does not provide construction dates, a detour schedule or a project picture.

Official Jackson Pike project page

Newtonsville Road bridge beam replacementFuture county project • Dates not published

Structure: C94-0.01. Listed as a future county project. No confirmed construction window or closure dates were available in the reviewed listing.

Official Newtonsville Road project page

Other future improvements to monitorTentative programs and projects in design

The county publishes future bridge and culvert work and a five-year paving forecast. CCTID also lists proposed Bach-Buxton Road roundabouts and a Deerfield Road / Woodville Pike roundabout. The Deerfield/Woodville project is in early design with construction funding not yet secured.

County future projects · Five-year paving forecast · CCTID projects in design

Dated closure notices on nearby travel routes

These are the dates posted by the County Engineer when this update was reviewed. Follow posted signs and check the official notices for changes.

Road / areaWorkPosted dates
Marathon-Edenton Road, Wayne TownshipWaterline relocation north of No. 9 RoadNovember 3–5, 2026
Johnson Road, Wayne TownshipBridge repairOctober 16–November 13, 2026; 7:30 a.m.–5 p.m.
Deerfield Road, Goshen / Miami townshipsWatermain connectionNovember 3–5, 2026
Branch Hill-Miamiville Road, Miami TownshipUtility connectionSeptember 28–November 30, 2026

View the official Marathon-Edenton closure notice and detour map (PDF)
View all county road closure notices

Earlier Owensville improvements

U.S. 50 / S.R. 132 intersection improvementsHistorical project information • May 2024 construction start listed

PID 107292: CCTID describes added turn lanes and updated traffic signals at the two intersections, with a May 2024 construction start and a $3,649,009.08 construction cost. Its page retains older construction wording. This is not a new 2026 closure announcement; ask CCTID to confirm present status.

Official aerial drawing of U.S. 50 and S.R. 132 intersection improvements
U.S. 50 / S.R. 132 project drawing. Source: CCTID.
Official aerial drawing of U.S. 50, S.R. 132 and Belfast-Owensville Road improvements
U.S. 50 / S.R. 132 / Belfast-Owensville Road project drawing. Source: CCTID.

Official intersection improvement project

Separate older paving work: ODOT’s April 22, 2025 notice described resurfacing Main Street, South Broadway and a section west of Owensville. Read the historical resurfacing notice.

Official offices and project resources

Clermont County Engineer

2381 Clermont Center Drive
Batavia, OH 45103
513-732-8857
Monday–Friday, 8 a.m.–4:30 p.m., except holidays.

Current projects
Future projects
Closures and detours

Clermont County TID

Transportation Improvement District
info@GoClermont.org

Contact the project office
Construction project list
Projects in design

ODOT District 8

Public Information
513-933-6517
D08.PIO@dot.ohio.gov

OHGO live road conditions
ODOT project search

Regional and federal planning

Ohio’s four-year STIP is jointly approved by FHWA and FTA. OKI’s regional TIP lists local projects and funding phases. No separate federal Owensville construction schedule was identified.

Ohio 2026–2029 STIP
OKI project listings
OKI project map
Federal Highway Administration

Report a local road concern

Contact Village Hall at 513-732-5350 to report road maintenance or transportation concerns in Owensville.